← Back to Projects
Featured Case StudyCompleted Technical Simulation StudyCritical-Power Microgrid & Resilience

Hospital Critical-Power Microgrid Optimization & ETAP Verification

Independent critical-power microgrid study for a 300-bed hospital, combining 8,760-hour load and grid-availability modelling, HOMER techno-economic optimization, outage-resilience assessment and ETAP time-series load-flow verification for a grid/PV/BESS/diesel architecture.

Engineering Scope

Technical work and responsibilities

  • Developed and reviewed an 8,760-hour hospital demand model with 1.20 MW peak demand, 780 kW average demand and a 650 kW critical-load requirement.

  • Modelled grid availability at 18 hours/day and assessed a defined four-hour outage window against the requirement for uninterrupted critical-load supply.

  • Evaluated PV capacities up to 1.2 MW, battery storage up to 2.5 MWh and PCS capacity up to 1 MW using HOMER techno-economic optimization.

  • Compared dispatch strategies and selected the lowest-NPC feasible architecture meeting the critical-load reliability requirement.

  • Developed the recommended architecture in ETAP, including PV, battery/PCS, grid interface, two diesel generators, critical and non-critical hospital loads.

  • Reviewed ETAP time-series load-flow behaviour and system operating quantities for the modelled electrical network.

  • Prepared annual demand, load-duration, monthly demand, monthly energy and outage-availability visualisations to communicate the engineering basis of the study.

Delivery Outcomes

Verified project results

  • Selected HOMER architecture: 1.2 MW PV, 2.2 MWh nominal battery storage, 704 kW system converter, two 648 kW diesel generators and a 1.2 MW grid connection using cycle-charging dispatch.

  • HOMER reported zero unmet electric load and zero capacity shortage for the selected configuration.

  • Reduced modeled net present cost from approximately $14.1 million for the base system to $9.63 million for the proposed system, with LCOE reduced from $0.180/kWh to $0.123/kWh.

  • Achieved a modeled 30.7% IRR, 3.72-year discounted payback and 3.25-year simple payback under the study assumptions.

  • Reduced modeled annual diesel consumption from 401,069 litres in the base system to 57,376 litres in the proposed configuration.

  • ETAP one-line and time-series load-flow modelling provided an electrical-system verification layer for the optimized critical-power architecture.

Technical Areas

Engineering methods and project disciplines

HOMER ProETAPPythonExcel8760 Energy ModellingTime-Series Load Flow
Hospital MicrogridCritical LoadGrid-PV-BESS-DieselEnergy ResilienceHOMER ProETAP8760 Load ProfileBattery StorageTechno-Economic OptimizationTime-Series Load Flow

Selected project evidence

Engineering Drawings

6 items

PDF

Engineering Drawings

ETAP Hospital Critical-Power One-Line Diagram

ETAP one-line and time-series load-flow model incorporating PV arrays, PCS and battery system, two diesel generators, grid interface, transformer, and separate critical and non-critical hospital loads.

Sep 2026

View Document →

Reports / PDFs

1 item

PDF

Reports / PDFs

HOMER Critical-Power Microgrid Simulation Report

HOMER report covering the selected system architecture, cost summary, electrical balance, PV and battery performance, grid purchases, diesel consumption and economic comparison with the base system.

Sep 2026

View Document →

More Case Studies

See how I’ve applied this experience across other projects.

Browse additional work in mini-grid delivery, distribution network design, power-system modelling, commissioning and field implementation.