Engineering Drawings
ETAP Time-Series Load-Flow One-Line Diagram PDF
Original ETAP one-line drawing for the modelled grid, diesel, PV and factory-load system.
Sep 2026
View Document →Independent engineering study for a manufacturing facility combining an 8,760-hour load and dispatch model, rooftop PV sizing and energy-yield simulation, and ETAP power-system studies for grid, diesel and PV operating scenarios.
Engineering Scope
Cleaned and structured an 8,760-hour annual load profile in Python, including grid-availability status and baseline grid/diesel dispatch.
Compared six PV capacities from 1.198 MWp to 2.874 MWp to assess solar utilisation, curtailment, diesel displacement and operating-cost savings.
Modelled the 2.874 MWp maximum-roof, zero-export PV scenario in PVsyst using 5,423 × 530 Wp modules and 22 × 100 kW inverters.
Developed the grid/diesel/PV electrical network in ETAP and evaluated load flow and time-series load-flow operating conditions.
Performed IEC 60909 three-phase short-circuit analysis and reviewed fault levels across the LV and 11 kV buses.
Completed an IEEE Std 80 ground-grid study to assess grounding arrangement, touch potential and step potential.
Delivery Outcomes
Modelled annual facility demand of 9,014.4 MWh from a complete 8,760-hour dataset, with 4,380 grid-available and 4,380 grid-unavailable hours.
PVsyst simulated 4,333.2 MWh/year of solar energy supplied to the load, 1,508 kWh/kWp/year specific production, 67.45% performance ratio and 48.07% solar fraction.
Python scenario analysis estimated a 74.4% reduction in baseline diesel-generator energy for the 2.874 MWp case, equivalent to about 1.17 million litres/year of diesel avoided under the study assumptions.
ETAP time-series results confirmed acceptable operating-voltage behaviour in the assessed scenario, while short-circuit and grounding studies provided fault-duty and electrical-safety checks for the modelled system.
Technical Areas
2 items
Engineering Drawings
Original ETAP one-line drawing for the modelled grid, diesel, PV and factory-load system.
Sep 2026
View Document →3 items
Reports / PDFs
PVsyst simulation report covering system configuration, annual energy results, losses and financial outputs.
Sep 2026
View Document →Reports / PDFs
ETAP report covering three-phase fault-current results for the modelled LV and 11 kV buses.
Sep 2026
View Document →Reports / PDFs
Ground-grid report documenting the modelled conductor and rod arrangement with touch- and step-potential checks.
Aug 2026
View Document →Engineering Portfolio
View additional renewable-energy, mini-grid, distribution-network and project-delivery assignments.